Rüzgâr investors were installed in the transmission line
]]30 July 2007-Mill
]]]In recent years, TEİAŞ did not confirm that the transmission capacity is full.
[[T]]Clean and source domestic, as well as thousands of megawatt wind energy investments in recent years due to the guarantee of state-of-the-of-the-art reception, resulting in electricity production and clear interest in the private sector, were installed in the transmission system. Since 2006, the Turkish Electrical Transmission Joint Company (TEIAŞ) for wind investments applied to the Energy Market Regulation Authority (EPDK) application did not have visa if it is pushable that the transmission capacity is full. The Rüzgâr Atlas is a pioneer in domestic and foreign investors by the Ministry of Energy, was shown in Çanakkale, Balıkesir and Ayvalik in Turkey’s most wind areas. In the report study by TEİAŞ for these regions, the wind power plants under 50 megawatts (RES) projects were included in the opinion that the electrical distribution system are not economical. THANK, indicating that the electricity is produced in the RES projects can be distributed to the region where they are located, because of the failure of the current transmission lines, therefore, it also requires companies to download the capacity they target in the RES projects. [[[T]] [[T][6][Lisans can be growing]]]TEİAŞ's decision creates a cold shower effect to waiting companies for investment, if it is expected to refuse the license applications of 'appealable bulan' EPDK. The owner of the RES project that requires 1 million euros per Megavat was surprised what they are going on. Thanks for waiting for a license from the EPDK to make money by selling electricity to the system where the Rüzgâr invests and the electricity to produce from here, complaining that the institution has started to invest this decision. EPDK decided to accept license applications until September 2007 because of its busy application, was waiting for for thousands of megawatt wind applications from this date. ]
The reason for wind is unpowerable'
]]Rüzgâr Energy and Water Power Plants Association (RESSİAD) President Tolga Informationn said that the TEİAŞ system remains unpowered for wind, but because these difficulties are not able to do from their budget, such a problem arises. Information, which explains some lines can be made by the private sector, said: "The volume cost of such lines is very dropping, as the power rises. These are the investments to be done before, but the resources of the state are certain. Can be applied to large projects. We have to everything from the state. The energy investors in the US perfume lines to city centers themselves. "The Information, which saves some errors," made applications without "Unfortunate and TEİAŞ. 'Do you have enough connections here in normal?' said.
]] They are waiting to sell 'Lisans'
]]]]Inspiration of General Manager of TEİAŞ, said they were given to 'olur' to about 5 thousand megawatts RES project, but even 100 megawatt projects were not built. Earlier, the companies who have been licensed from EPDK were waiting to sell them, said that this situation also blocks the current cryptocurrency, said: "I never resorted to the license of real investors. In the last period, real investors came to the license. All license areas first try to their sell licenses. These are not subject to time with those waiting to invest and sell licenses. Turkey's hand lever is connected. "
]]] [
]]http://www.milliyet.com.tr/2007/07/30/economic/axeko01.html]